Phase 2 of the improvement works continues to go well.
Today we will be working outside "Tilleys" sandwich shop at the Pheasant Street end of Lowesmoor installing a chamber box for the traffic lights and ducting to the footway. The visibility fence will also be taken down whilst alterations are being made to the crossing.
Tomorrow we will continue working outside "Tilleys" sandwich shop with the installation of ducting and installation of new traffic light socket and loop box.
We thank you for your patience and understanding whilst this work is being carried out.
The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the works, he will be able to answer any queries that you may have.
We will be updating this blog on a daily basis |(Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed. www.twitter.com/roadworks_info