Thursday, 11 April 2013

Lowesmoor traffic signal,Footway and Carriageway improvement works

The improvement works continue to go to plan with the new traffic lights switched on yesterday at the top end of  Lowesmoor.

Today we will continue working outside "Tilleys" sandwich shop installing ducting and kerbing.


Tomorrow we will be working on the splitter island at the Pheasant Street junction with Lowesmoor. We will be installing ducting and light socket box for the new traffic lights.

We thankyou for your patience and understanding whilst this work is being carried out.

The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the works, he will be able to answer any queries that you may have.

We will be updating this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed. www.twitter.com/roadworks_info