Today we have setup 2 way temporary traffic lights at the junction of Pheasant Street and Lowesmoor. These have been setup to allow us to excavate the island and then lay the base and surface course material.
Our plan for tomorrow (subject to weather), will be to lay tactile paving in the vicinity of the American Golf Shop and Lifestyles.
We would like to thank you for your patience and understanding whilst this work is being carried out. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the works, he will be able to answer any queries that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
We will be updating this blog on a regular basis (Monday to Friday) so please ensure you visit on a regular basis for updates on the progression of this scheme. Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twtter.com/roadworks_info