Thursday, 14 March 2013

Lowesmoor traffic signal,Footway and Carriageway improvement works

Today we started work early before opening to  install ducting across the vehicular entrance at AV Band and will carryon installing the ducting and loop boxes towards the traffic lights.
Tomorrow we plan to install some kerbing ready for the new crossing on the same side of the road as AV Band. This will be carried out without any lane closures.
There will be a road closure for 4 days next week starting on Monday 18th March, 2013. This will be from the top of Sansome Walk as you turn left into Lowesmoor past "Fat Boy Trims" hairdresser's.  This is to enable us to excavate and install the ducting in the road ready for the pedestrian crossing.

Evacting on splitter island  last Friday 8th March, 2013

We appreciate your patience and understanding whilst we carryout these works.

Our Liaison Officer will be regularly available on site in Lowesmoor during the works to listen to any concerns or issues.

This blog is updated on a daily basis so please visit regularly for the most up to date information.

No comments:

Post a Comment