Wednesday, 9 January 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Improvement and maintenance works have been scheduled to be undertaken at Lowesmoor, these works are programmed to commence 14th January 2013 and will last for approximately three months.

The scheme, to lay traffic signal cable ducting, footway and carriageway works will be carried out in three phases. These phases are planned as follows:-

Phase 1 - Lowesmoor / City Walls Road
This phase involves the installation of new ducting for the traffic signals at the junction of Lowesmoor and City Walls Road.



Phase 2 - Lowesmoor / Pheasant Street
This phase involves the installation of new ducting for the traffic signals at the junction of Lowesmoor and Pheasant Street.



Phase 3 - Lowesmoor
This phase involves improvement works of the footway and carriageway along Lowesmoor.



Each day a Public Liaison Officer will visit site, they will be available to answer any queries that you may have. The Foreman, who will be based on site, will also be available to provide updates on the progress of the works plus answer any questions.

We will update this blog on a daily basis (Monday to Friday), once the works commence. Please ensure you make return visits regularly for further information on the progression of these works, if required you can telephone our customer care line 01905 761176 for additional information.

We would like to thank you in advance for your co-operation whilst these improvement works are being carried out.