Friday, 20 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

The Lowesmoor Improvement scheme is now completed. We would like to thank you for all your patience and understanding whilst we carried out these works. 
 
 
Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info. We can also be contacted on our Customer Care Line, 01905 761176, or by email at roadworks.info@ringway.co.uk

Thursday, 19 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

Today we will be pressure washing the footpaths and having a general tidy up throughout Lowesmoor & City Walls Road site.
 
 
 
We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of thee works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

Wednesday, 18 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

The barrier replacement on City Walls Road has been completed and lane closure is removed.

Today we are painting existing posts along City Walls Road and replacing damaged tactiles by Silver Street Carpark.


 
 
We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of thee works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

Tuesday, 17 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

The barrier replacement and lane closures on City Walls Road is continuing and still on programme to finish by October.
 
 

We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of these works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

Monday, 16 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

The barrier replacement works along City Walls Road is progressing well to programme.
We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of these works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

Friday, 13 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

Works are still on course with the barrier replacement along City Walls Road.


We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of these works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info

Thursday, 12 September 2013

Lowesmoor traffic signal, footway and carriageway improvement scheme

Lowesmore is now fully open with all programmed works completed.

The barrier replacement and lane closures on City Walls Road is continuing and still on programme to finish by October.

 
We would like to thank you for your patience and understanding whilst we carry out these works. The Public Liaison Officer for this scheme is Terry Godwin who will be on site regularly throughout the duration of these works, he will be able to answer any questions that you may have. We can also be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk

We will continue to update this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme. Information on other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info