Thursday, 28 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works



Today we are working at the juncion from Lowesmoor to City Walls Road, re-instating the trench that was built to install the ducting. We will also be working on the right hand side of the large splitter island as you are leaving Lowesmoor installing ducting, kerbing and socket for traffic signals.

Tomorrow we will be working on the footway outside the site office installing ducting ,kerbing and post socket for traffic signals.
The bus lane will re-open tomorrow Friday 1st March, 2013.

We appreciate your patience and understanding whilst we carryout these works.
The blog is updated regularly so please visit daily for up to date information.

Wednesday, 27 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we are working on the big island at the juncion from Lowesmoor to City Walls Road and the small island to the left leading into Silver Street. We will be installing some ducting and a chamber for the loop box for the signals. Two traffic light post sockets will also be installed.
 
The bus lane will re-open on Friday 1st March, 2013.

We appreciate your patience and understanding whilst we carryout these works.
 
The blog is updated regularly so please visit daily for up to date information.

Tuesday, 26 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works



Today we are working on the big island at the juncion with City Walls Road and Lowesmoor. We will be laying isolated kerbing, completing the ducting and installing two new Post Sockets for the traffic signals.

Tomorrow we will be working on the same island at the juncion with City Walls Road and Lowesmoor installing a chamber for the loop box for the signals.
The bus lane will be closed until Thursday 28th February, 2013.

We appreciate your patience and understanding whilst we carryout these works.
The blog is updated regularly so please visit daily for up to date information.

Monday, 25 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we are working on the Sansome walk side of Lowesmoor. We are laying a base course behind the kerbs on the bus lane. Dropped kerbs are also being installed on the pedestrian crossing on this side of Lowesmoor. We will continue with this installation tomorrow.
 
This work is being carried out within the bus lane closure.

We appreciate your patience and understanding whilst we carryout these works.

Thursday, 21 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we have started to install the road crossing from the splitter island at the Sansome walk side of Lowesmoor. We will continue with this installation tomorrow.

Kerbing works will also be undertaken within the bus lane closure.

We appreciate your patience and understanding whilst we carryout these works.

Wednesday, 20 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

The bus lane is being closed for seven days, this is to enable works to commence on the splitter island at the Sansome Walk side of Lowesmoor; kerbing works will also be undertaken within the closure.

We appreciate your patience and understanding whilst we carryout these works.

Monday, 18 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

The works continue to go to plan. Today we will be working outside the Private Shop towards the large splitter island to Silver Street under a lane closure to enable us to install ducting across the road.
 
This blog is updated on a daily basis so please visit for the most up to date information on progress.

Friday, 15 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we will working on City Walls Road outside our site office. We will be installing a new contoller box for the new traffic lights and ducting to the controller for these. The electrics will also be installed to the feeder pillar.
 
On Monday and Tuesday next week we will be working outside the Private Shop under a lane closure to install ducting across the road.

This blog is updated on a daily basis so please visit for the most up to date information on progress.

Thursday, 14 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we will be installing ducting in the footway from the Private Shop up to City Walls Road.

Tomorrow we plan to install ducting along City Walls Road in the footway outside our site office.

This blog is updated on a daily basis so please visit for the most up to date information on progress.

Wednesday, 13 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we will complete the installation of ducting on the long splitter island as you approach City Walls Road from Lowesmoor, in front of the car park.
Tomorrow we will be installing ducting in the foot way from the Private Shop up to City Walls Road.

The blog is updated on a daily basis so please visit for the most up to date information on progress.

Tuesday, 12 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

The installation of ducting on the long splitter island as you approach City Walls Road from Lowesmoor, in front of the car park continues today.

The blog is updated on a daily basis so please visit daily for up to date information.

Monday, 11 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we are continuing with  the installation of ducting on the long splitter island as you approach City Walls Road from Lowesmoor, in front of the car park. It is planned to continue with the installation in this area again tomorrow.


We will continue to update this blog on a daily basis so please visit daily for up to date information.

Friday, 8 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today the installation of ducting will be carried out on the long splitter island as you approach City Walls Road from Lowesmoor, in front of the car park. It is planned to continue with the installation in this area again on Monday.

We will continue to update this blog on a daily basis so please visit daily for up to date information.

Thursday, 7 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works


Today the installation of the ducting on the largest splitter island on City Walls Road continues.
It will not be necessary to make any lane closures whilst this work is being carried out.


We will continue to update this blog on a daily basis so please visit daily for up to date information.

Wednesday, 6 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today will are continuing with the installation of  ducting on the largest splitter island on City Walls Road .
 
It will not be necessary to make any lane closures whilst this work is being carried out.

We will continue to update this blog on a daily basis so please visit daily for up to date information.

Tuesday, 5 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today ducting works are being carried out on the largest splitter island on City Walls Road.
 
It will not be necessary to make any lane closures whilst this work is being carried out.

We will continue to update this blog on a daily basis so please visit daily for up to date information.

Monday, 4 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we will be continuing with the installation of ducting to the largest splitter island on City Walls Road . No lane closures will be necessary whilst this work is being carried out.

We will continue to update this blog on a daily basis so please visit daily for up to date information.

Friday, 1 February 2013

Lowesmoor traffic signal, footway and carriageway improvement works

Today we are continuing with the installation of ducting on the central reservation on City Walls Road towards Lowesmoor. We will also be installing three inspection chamber boxes.
On Monday we will be continuing with the installation of ducting to the largest splitter island on City Walls Road . No lane closures will be necessary whilst this work is being carried out.

We will continue to update this blog on a daily basis so please visit daily for up to date information.